We are excited to report that here has been a significant amount of civil works completed since out last update.

What’s been done?

          All drainage, sewer, water and earthworks 95% complete

          Light poles have been installed

          All kerbing poured with base course crushed rock on the roads

          3.5 km of footpath construction well under way

          Electrical cabling installed and trenches backfilled

Across the next few weeks, our super fast fibre to premise NBN will be completed along with the completion of all concrete works.

Another significant milestone is asphalting works both internally and in Harpers Lane, scheduled for completion in late April / early May.

Did you know that we are also installing a water booster pump station that will ensure excellent pressure throughout the estate?

We are also proud to announce that the contract for the 1.6km of post and rail fence has been awarded to Polivin Fencing and is scheduled to commence in early June.

 

We will shortly be going to tender on the balance of the landscape works which among other things include:

          550 large trees (mix of ornamental and native)

          40,000 native plants within the wetlands and reserve

          Feature picnic shelter overlooking wetlands

          Manicured nature strips and reserves

 

For more information please visit Holly from Oliver Hume onsite from 11am – 5pm Saturday and Sunday or phone 03 9684 8119